Practice Questions on Time and Work with Multiple Methods and Tricks - Experts Advice

Experts+Advice

An Advice can change your life!

Practice Questions on Time and Work with Multiple Methods and Tricks

Share This

Time and Work

Example 1: If 3 men or 4 women can reap a field in 43 days, how long will 7 men and 5 women take to reap it?

Solution:  Method 1:  3 men in 43 days reap = 1 field
   ⇒ 3 men can reap in 1 day = 1/43 of the field
   ⇒ 1 men can reap in 1 day = 1/(43x3) of the field
Similarly, 4 women in 43 days reap = 1 field
   ⇒ 4 women can reap in 1 day = 1/43 of the field
   ⇒ 1 women can reap in 1 day = 1/(43x4) of the field
Therefore, 7 men and 5 women can reap in 1 day = 7 x 1/(43x3) + 5 x 1/(43x4) = 1/12th of the field
   ⇒ 7 men and 5 women will reap the whole field in = 12 days

 Method 2:  3 men = 4 women
   ⇒ 1 man = 4/3 women
   ⇒ 7 men = 7 x 4/3 women = 28/3 women
   ⇒ 7 men + 5 women = (28/3 + 5) women = 43/3 women
Now the question is: If 4 women can reap a field in 43 days, how long will 43/3 women take to reap it?
Now using basic formula: (M1 x D1) = (M2 x D2)
   ⇒ 4 x 43 = 43/3 x D2
   ⇒ D2 = 12 days

Example 2: A is twice as good a workman as B. Together, they finish the work in 4 days. In how many days can it be done by each separately?

Example 3: 10 men can finish a piece of work in 10 days, whereas it takes 12 women to finish it in 10 days. If 15 men and 6 women undertake to complete the work, how many days will they take to complete it?

Example 4: A builder decided to build a farmhouse in 40 days. He employed 100 men in the beginning and 100 more after 35 days and completed the construction in stipulated time. If he had not employed the additional men, how many days behind schedule would it have been finished?

Example 5: A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were employed and the work was finished one day earlier. How many days would it have been delayed if 5 more men were not employed?

Example 6: 38 men, working 6 hours a day can do a piece of work in 12 days. Find the number of days in which 57 men working 8 hours a day can do twice the work. Assume that 2 men of the first group do as much worked in 1 hour as 3 men of the second group do in 1.5 hours.

Example 7: A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in how many days?

Example 8: A and B can do a work in 12 days, B and C in 15 days and C and A in 20 days. If A, B and C work together, they will complete the work in?

Example 9: A and B working separately can do a piece of work in 9 and 15 days respectively. If they work for a day alternatively, with A beginning, then the work will be completed in how many days?

Example 10: A, B and C can do a piece of work in 30, 20 and 10 days respectively. A is assisted by B on one day and by C on the next day, alternately. How long would the work take to finish?

Example 11: A can do a piece of work in 8 days which B can destroy in 3 days. A has worked for 6 days, during the last 2 of which B has been destroying; how many days must A now work alone to complete the work?

Example 12: A man, a woman and a boy can complete a job in 3, 4 and 12 days respectively. How many boys assist 1 man and 1 woman to complete the job in 1/4 of a day?

Example 13: A can do a piece of work in 70 days and B is 40% more efficient than A. The number of days taken by B to do the same work is?

Example 14: A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs 3200. With the help of C they completed the work in 3 days. How much is to be paid to C?

Example 15: A man and a boy recieved Rs 800 as wages for 5 days for the work they did together. The man's efficiency in the work was three times that of the boy. What are the daily wages of the boy?



Comment Using!!

No comments:

Post a Comment

Pages